Friday, 03 March 2017 13:45

Construction Update - Replacement Tree Plantings

The proposed tree replacement locations have been laid out by the engineer per the contract plans. The engineer will meet the Village's arborist Friday (3/3) to go over the locations and revise the locations if necessary. The contractor has ordered all the trees from local nurseries and appropriate reports have been submitted to IDOT. 

 

Moving forward and as soon as weather permits, the contractor will commence with the tree installation. The contractor will also continue with any remaining punch list items that were left over from last year's work.


Project Progress:
99%