Monday, 05 December 2016 19:18

North Ave Substantial Completion

We are pleased to inform you that we are substantially complete with the North Avenue Reconstruction project in your neighborhood.

A walk-through with Village staff has been completed and a punch list of minor clean up and outstanding work items to be completed has been prepared and submitted to the Contractor.

Please note that the punch list items and tree plantings will be completed in the spring of 2017 with a final inspection of all work completed immediately thereafter. Any work not deemed acceptable will be removed and replaced in kind.

Throughout the duration of this project, we repeatedly requested your patience and cooperation. At times operations seemed a bit chaotic, with many new faces and vehicles in the neighborhood for the past several months, and we thank you for treating them all with respect as we hope that they did for you. Village staff, the Contractor and the onsite engineers from Gewalt Hamilton Associates greatly appreciate the patience you have all shown and are optimistic that you will enjoy the return of tranquility to your neighborhood.


Project Progress:
99%