Friday, 11 November 2016 21:09

Construction Update - 11/11/2016

Work completed:

  • Arteaga has installed pulverized topsoil within the parkways along North Avenue.
  • Kim Construction has completed sanitary manhole lining operations at various locations.
  • Peter Baker & Son installed hot-mix asphalt surface course throughout the project limits.
  • Permanent pavement markings have been installed per the approved Engineering plans.
  • The detour and all applicable traffic control signage has been removed and the roadway opened to all traffic.
  • This contract is considered substantially completed.

Anticipated schedule for next week:

  • Arteaga will install sod within the parkways along North Avenue and reinstall all brick driveways and sidewalks throughout the project limits.
  • Berger will complete miscellaneous applicable punch list items.
  • Percentage Complete: 90%

Schedule for next spring:

  • Arteaga will install tree plantings per the approved Engineering plans. 
  • Berger and subcontractors will complete any remaining punch list items not completed this fall.

Neighborhood Impacts:

  • Construction operations will require moving daily lane closures and present minimum delays for vehicular traffic along North Avenue.

Project Progress:
99%