Friday, 15 July 2016 19:35

Update for week of July 18, 2016

Construction signage has been erected and tree removal began the week of July 11th. Looking forward, erosion control measures will be installed the week of July 18th, in preparation for water main installation which take place the following week.

Construction activities will begin to ramp up over the next two weeks that will result in heavy truck traffic and the mobilization of large construction equipment. Please avoid walking and riding bicycles within the construction zone, as loose gravel presents hazards for both pedestrians and cyclists. Motorists should select alternative routes to avoid construction.

 


Project Progress:
99%