North Ave Reconstruction Project

This project is a joint venture between the Villages of Deerfield and Bannockburn. Due to this section of road being identified as a major collector route, this project qualified for and has received Federal funding participation.

We are pleased to announce that preliminary work will begin July 5, 2016

The work consists of storm sewer, sanitary sewer, and water main improvements, proposed curb and gutter installation, new asphalt pavement installation, driveway apron installations, new tree installation, and landscape restoration along North Avenue from Wilmot Road to Telegraph Road.

The roadway will be closed to all thru traffic with a posted detour throughout the duration of the project. While the operations will likely create brief delays in traveling your street or entering/exiting driveways, access to all homes will be maintained.

In accordance with Village Code, construction working hours are from 7:00 am to 7:00 pm during the week and 8:30 am to 7:00 pm on Saturday. We anticipate the project will be completed by the end of November, 2016 with remaining landscape work to be completed in the Spring of 2017.

As with any construction project, there will be inconveniences at times and we thank you in advance for your patience and cooperation. The Village and the Contractor are working together to minimize the disruption and inconvenience you will experience.


Project Progress:
99%